Location: Spain - 2008
For maintenance & painting opf wide body aircraft
The decision was taken in 2007 that the existing painting facility needs to be refurbished. The reason is that the existing teleplatforms which have been provided by a competitor do not fulfill the requirements in terms of operator safety and reliability anymore. CTI Systems' scope of work consisted of the dismantlement of the existing system and provision of four new bridge cranes with one dedicated platform per crane. One of the biggest challenges was the short available period for all required installation and commissioning tasks of less than two months.