Fully automatic cataphoretic dip and powder coating installation

Location: Germany

For trailers and trailer parts

The system consists of eighteen (18) trolleys, two (2) lifting stations, two (2) chain conveyors, two (2) diagonal carriers and four (4) transversal bridges.


Installation date:   2007


The company manufactures trailers from different types. Started in 1996, CTI delivered the handling equipment for the paint shop.

Increasing business and reaching a maximum capacity required modernization and expansion of the system in 2006.

Two years later, the next step to move up the capacity was required.